University Drive Median Project

  • Project typeCity Project
  • Completion DateJune 14, 2021

The landscape project will begin on University Drive from Southgate Boulevard to NW 28th Street. Each median require first the removal of trees before installment of the new landscape commences. 

Lane Closures

The closures will occur only near the medians where work is being completed. Closures will be in increments of approximately 900' at a time.

List of Medians and Timeline

March 23 to April 5

  • SW 1 Ct to Riverside Dr
  • Riverside Dr to NW 4 St

April 6 to April 7

  • NW 6 Ct to W Atlantic Blvd

April 8 to April 12

  • W Atlantic Blvd to Coral Square Mall Blvd

April 15 to April 22

  • Coral square Mall Blvd to Ramblewood Dr
  • Ramblewood Dr to Maplewood Blvd

April 16 to April 20

  • Maplewood Blvd to Shadowood Blvd

April 21 to April 28

  • Shadowood Blvd to NW 16 St
  • NW 16 St to 1st Southern Bank

April 29 to May 3

  • 1st Southern Bank to NW 19 St

May 4 to May 5

  • NW 20 St to Royal Palm Blvd

May 6 to May 7

  • Royal Palm Blvd to NW 25 Ct

May 10 to May 16

  • NW 25 Ct to NW 28 St

May 19 to June 9

  • Mulch all medians

 

Location

University Drive, Coral Springs 33065  View Map

Google Map