University Drive Mobility Improvement Project

  • Project typeFDOT Project
  • Project value$3.5 million
  • Project scheduleJanuary 10, 2022 - Fall 2022

As part of the University Dr. Mobility Improvement project, the Florida Department of Transportation’s District Four will begin construction on University Drive between 28th Street and Sample Rd. 

PROJECT IMPROVEMENTS

  • Widening southbound SR 817/University Drive from NW 32nd Street to SR 834/Sample Road to construct a bus bay and implement a dedicated right-turn lane at NW 32nd Street
  • Upgrading northbound pavement markings to designate 4-foot bicycle lanes between NW 28th Street and NW 31st Court and 7-foot bicycle lanes between NW 31st Court to Sample Road
  • Upgrading southbound pavement markings to designate 7-foot bicycle lanes from Sample Road to NW 32nd Street and 4-foot bicycle lanes from NW 32nd Street to NW 28th Street
  • Upgrading traffic and pedestrian signals at the following intersections: NW 28th Street, NW 31st Court and SR 834/Sample Road
  • Installing 11 light poles along the project corridor
  • Upgrading drainage, and signage
  • Milling and resurfacing along the project corridor

TRAFFIC IMPACTS

  • Lane closures may occur in each direction, 9:00 a.m. to 4:00 p.m., Monday through Saturday.
  • Lane closures may occur in each direction, 9:00 p.m. to 5:30 a.m., Sunday through Thursday.
  • Access to businesses and residences will be maintained at all times.

 

 

 